Hello All,
We are having trouble with "what-if" material analysis in QAD. We need to ask questions like: "What if we adjust the manufacturing schedule for certain lots?", "What if key materials expire on future dates affecting supply on hand?", or "What if a lot fails and we need to scrap large quantities of sub-assemblies?".
Q1: How do you perform simulations in QAD without impacting actual work orders and purchase orders?
Q2: Have you built an Excel model based on QAD MRP data to quickly see the impact on future days-on-hand for buy
parts? Is there an already developed product in the market that integrates with QAD to achieve this?
Any insights would be appreciated as we work on resolving these issues.